Project Progress Report
Mission College
Project Status:
- Scope of work planned for completion at the same time as project MC 34.
- Board approval of Sandis' electrical/civil contract completed on April 16, 2009
- Anticipate coordination of users meetings to address scope and schedule through out summer 2009
- Project Phase estimated completion: 10%
Completed This Period
- SOI distribution to the District's Pool of Architects
- Board approval of architect firm April 2009
Activity Planned for Next Period
- Commence Preliminary Plans to be completed by August 2009.
- DSA submittal August/September 2009
- Estimated DSA approval November/December 2009
Schedule Summary
IPP Submittal:03/2009
FPP Submittal:04/2009
Preliminary Plans:06/2009
Working Drawings:07/2009
DSA Submittal:09/2009
DSA Approval:11/2009
Bid:12/2009
Award of Bid:02/2010
Begin Construction:03/2010
End Construction:08/2010
DSA Closeout:09/2010
Budget Summary
Funding Source
Measure H$1,771,721
State Funds
Project Budget$1,771,721
Encumbered$100,611
Expenditures
Budget Balance$1,671,110
Construction Budget$1,316,635
Bid Awards
Executed C/Os
Construction Balance$1,316,635